How we're changing

Barbican Renewal

Barbican Renewal May public consultation
19 May - 2 June 2025

This consultation is now closed for responses – thank you to everyone who contributed. We are currently analysing all the feedback and comments provided. These results will be published later in summer 2025.

What’s next?

We intend to submit our planning and listed building consent applications later in summer 2025. Public consultation will be held on this by the City of London Corporation ahead of a planning decision expected in the autumn.

Subject to consents, further project planning and detailed design will take place in the remainder of 2025 and 2026 ahead of construction expected from 2027 onwards.

About Renewal

Barbican Renewal is our plan to ensure every part of the Barbican Centre’s iconic site is restored, revitalized and relevant for future generations.  

The Barbican is a Grade II listed Brutalist icon, recognised as one of the UK’s architectural treasures. Since we opened our doors in 1982, we have become a world-renowned destination, offering a creative programme of unique breadth in spaces of exceptional architectural significance.  

At the heart of Renewal is a commitment to celebrating the architectural vision and heritage of the Centre, with a programme of sensitive conservation and upgrade to bring the buildings back to their best, while also delivering a place that is truly inclusive, sustainable and resilient. 

Over the past four decades the Barbican Centre buildings have deteriorated significantly. Through Renewal, building systems and ageing materials will be upgraded and restored, while underused areas of the site will be unlocked, releasing their full potential for public, civic and creative use.   

Barbican Renewal is already underway, with essential improvements being made to systems and visitor facilities. Thanks to additional funding of £191m from the City of London Corporation, we are now able to commit to delivering the next major phase of work as part of a five-year programme to forge the Centre’s future.  

The City contribution represents around 80% of the amount needed for the full five-year plan, and will support critical repairs and upgrades. A major fundraising campaign will be launched in 2025 to enable complete restoration and refurbishment of key public spaces including the unique brutalist foyers, lakeside terrace, and conservatory – the largest glasshouse in central London. Funding raised will open up these celebrated spaces to all, deliver major new creative community and learning activities, and make significant sustainability improvements to ensure net-zero commitments are met.  

Subject to planning permission, construction will begin in 2027 with this first phase complete in 2030, ahead of the Barbican’s 50th anniversary. We will keep this page updated with information as the projects develop. 

Sign up for updates

Get in touch

You can contact the Barbican Renewal team by emailing [email protected]

Project partners

Allies and Morrison logo
Logo of Asif Khan Studios
Logo for Buro Happold
Text logo saying Alan Baxter
Text logo saying ARUP
Charcoal Blue logo
Logo for Harris Bugg Studio
The Planning Lab logo